Phase 7: Acceptance, go-live and the phase 1 close-out

This phase agrees the acceptance criteria with the Authority, runs user acceptance testing with the Authority's testers, and fixes each defect through the reviewed pipeline.

No picture for this component.

Plan · The RFP and the plan · Phases

Phase 7: Acceptance, go-live and the phase 1 close-out

This phase agrees the acceptance criteria with the Authority, runs user acceptance testing with the Authority's testers, and fixes each defect through the reviewed pipeline.

  1. Sources
  2. Interchange
  3. Twin
  4. Screens
  5. Plan
Kind
Plan
Status
not linked
Airport layer
not linked
Airport area
not linked
System
not linked
Sensor type
not linked

Open the detail

Level 2 of 3 This component, complete on its own. Its files, sources and tests are the detail below. Open the detail

This phase agrees the acceptance criteria with the Authority, runs user acceptance testing with the Authority's testers, and fixes each defect through the reviewed pipeline. It matters because 2027-06-30 is the hard end of the funded window, and payment depends on each deliverable carrying written acceptance.

Dates
2027-05-17 to 2027-06-30
Requirements delivered
6
Work units
6
Needs
Needs P6
Work units (6)
UnitTitleDatesRFPNeeds
WU-7-1User acceptance plan and criteria2027-05-17 to 2027-05-28B iii, C 7.1DEP-18
WU-7-2UAT execution and defect log2027-06-01 to 2027-06-11B iii, C 7.1DEP-18
WU-7-3Defect fixes through the reviewed pipeline2027-06-07 to 2027-06-18B v, C 7.4
WU-7-4Production go-live with failover and restore drills2027-06-21 to 2027-06-23B iii, C 7.1DEP-19
WU-7-5Written acceptance and baseline comparison2027-06-24 to 2027-06-30C 2.3, C 7.1, RFP 3DEP-23
WU-7-6Grant close-out package2027-06-21 to 2027-06-30B vi, RFP 3DEP-21
WU-7-1: User acceptance plan and criteria

Draft the user acceptance plan with test cases and pass criteria traced to the validated requirements and kickoff baselines, ready for the Authority to sign by DEP-18 (REQ-IMP-046).

Depends on
none
Authority dependencies
DEP-18
Traces to
REQ-SFB-052
Functional requirements
4
WU-7-2: UAT execution and defect log

Run acceptance testing on staging with the Authority's testers, recording a pass or a logged defect against each criterion in the UAT record (REQ-IMP-047).

Depends on
WU-7-1
Authority dependencies
DEP-18
Traces to
REQ-SFB-052
Functional requirements
4
WU-7-3: Defect fixes through the reviewed pipeline

Fix each logged UAT defect through pull requests that need a reviewer and pass CI checks, then redeploy to staging for retest (REQ-IMP-048).

Depends on
WU-7-2
Authority dependencies
none
Traces to
REQ-SFB-068
Functional requirements
4
WU-7-4: Production go-live with failover and restore drills

Put production in service on the Authority's go-live decision and pass failover and restore drills on production, filing the drill records (REQ-IMP-049).

Depends on
WU-7-3
Authority dependencies
DEP-19
Traces to
REQ-SFB-069
Functional requirements
0
WU-7-5: Written acceptance and baseline comparison

Compare the phase 1 measures with the kickoff baselines in a measures report and obtain the Authority's signed acceptance (REQ-IMP-050).

Depends on
WU-7-4
Authority dependencies
DEP-23
Traces to
REQ-SFB-052, REQ-SFB-058
Functional requirements
4
WU-7-6: Grant close-out package

Assemble the state appropriation close-out package from filed evidence so each deliverable carries its written acceptance, submitted by 2027-06-30 (REQ-IMP-051).

Depends on
WU-7-5
Authority dependencies
DEP-21
Traces to
none
Functional requirements
3
Requirements delivered (6)
IdRequirementAcceptanceEvidence
REQ-IMP-046The user acceptance plan and its criteria agreed with the Authority.the criteria are signed before testing starts.the acceptance plan.
REQ-IMP-047User acceptance testing with the Authority's testers, with our support.each criterion has a pass or a logged defect.the UAT record.
REQ-IMP-048Defects from acceptance testing fixed through the pipeline, each reviewed before release.no change merges without a reviewer.the issues and pull requests.
REQ-IMP-049Go-live: production in service, with a failover and a restore drill passed.both drills pass on production.the drill records.
REQ-IMP-050Acceptance signed, and the measures compared with the kickoff baselines.the Authority signs acceptance.the acceptance record and the measures report.
REQ-IMP-051The phase 1 close-out package for the state appropriation, assembled from the evidence already filed under the grant agreement's terms.each deliverable carries its written acceptance.the close-out package.