Phase 8: Support and the next asset classes, rest of year 1
It adds the next asset classes by configuration at the pace the Authority sets (DEP-22, needed by 2027-07-01), with no rebuild of phase 1, and offers data services by labour category.
It adds the next asset classes by configuration at the pace the Authority sets (DEP-22, needed by 2027-07-01), with no rebuild of phase 1, and offers data services by labour category.
Level 2 of 3 This component, complete on its own. Its files, sources and tests are the detail below. Open the detail
It adds the next asset classes by configuration at the pace the Authority sets (DEP-22, needed by 2027-07-01), with no rebuild of phase 1, and offers data services by labour category. It closes by setting the year 2 roadmap with the Authority from the phase 1 measures and the backlog ranking.
Dates
2027-07-01 to 2028-01-31
Requirements delivered
5
Work units
6
Needs
Needs P7
Work units (6)
Unit
Title
Dates
RFP
Needs
WU-8-1
Run the three environments for the rest of year 1
2027-07-01 to 2028-01-31
B vi, C 7.4
WU-8-2
Stand up post go-live support
2027-07-01 to 2028-01-31
B v, C 7.4
DEP-22
WU-8-3
Record the Authority's order of later work
2027-07-01 to 2028-01-31
C 1.3, C 5.10, RFP 6.16
DEP-22
WU-8-4
Add the next asset classes by configuration
2027-07-01 to 2028-01-31
C 1.3, C 5.10, RFP 6.16
DEP-22
WU-8-5
Provide data services on request
2027-07-01 to 2028-01-31
B vi, C 4.5, RFP 10.4.6
DEP-22
WU-8-6
Set the year 2 roadmap with the Authority
2027-10-01 to 2028-01-31
B iii, C 7.4
DEP-22
WU-8-1: Run the three environments for the rest of year 1
Depends on
none
Authority dependencies
none
Traces to
REQ-SFB-069
Functional requirements
0
WU-8-2: Stand up post go-live support
Set up the support log, the issue intake and the help desk built from the product's documents, so upgrades, technical support and platform maintenance are met under the contract terms (REQ-IMP-053).
Depends on
WU-8-1
Authority dependencies
DEP-22
Traces to
REQ-SFB-053, REQ-SFB-067, REQ-SFB-068
Functional requirements
4
WU-8-3: Record the Authority's order of later work
Capture the Authority's DEP-22 order and pace for the next asset classes and processes, with who set it, as the planning input for the configuration work.
Depends on
none
Authority dependencies
DEP-22
Traces to
REQ-SFB-056
Functional requirements
4
WU-8-4: Add the next asset classes by configuration
Bring each next asset class and process in through the point registry, supplier standard and object model in the Authority's order, with a change record per class proving no rebuild of phase 1 (REQ-IMP-054).
Depends on
WU-8-1, WU-8-3
Authority dependencies
DEP-22
Traces to
REQ-SFB-056
Functional requirements
4
WU-8-5: Provide data services on request
Set up the request log and labour-category recording so staff are helped to gather, refine and consolidate data in the interfaced systems (REQ-IMP-055).
Depends on
WU-8-2, WU-8-3
Authority dependencies
DEP-22
Traces to
REQ-SFB-055
Functional requirements
4
WU-8-6: Set the year 2 roadmap with the Authority
Compare the phase 1 measures against the kickoff baselines, combine them with the backlog ranking, and agree a roadmap that orders each year 2 item with its value (REQ-IMP-056).
Depends on
WU-8-3, WU-8-4, WU-8-5
Authority dependencies
DEP-22
Traces to
REQ-SFB-057
Functional requirements
4
Requirements delivered (5)
Id
Requirement
Acceptance
Evidence
REQ-IMP-052
the environments stay healthy and the bill tracks the model.
the monthly cost and health report.
REQ-IMP-053
Post go-live support: upgrades, technical support, issue resolution, platform maintenance and the help desk built from the product's documents.
support terms met as the contract sets them.
the support log.
REQ-IMP-054
The next asset classes and processes added at the pace the Authority chooses, each following the phase 1 standard with no rebuild.
a new asset class added by configuration.
the change record.
REQ-IMP-055
Data services on request, helping staff gather, refine and consolidate data in the interfaced systems, by labour category.
each request has its labour category and hours recorded.
the data services log.
REQ-IMP-056
The roadmap for year 2 set with the Authority from the phase 1 measures and the backlog ranking.