AirfieldpathOrlando Sanford International

3.22 · The RFP and the plan · Phases

Phase 9: Year 2: every unit of the five classes, and the next systems

Phase 9 scales the phase 1 samples to every unit the Authority owns across HVAC, boarding bridges, baggage, vertical transportation and airfield, in the order the Authority sets.

No picture for this component.

Plan · The RFP and the plan · Phases

Phase 9: Year 2: every unit of the five classes, and the next systems

Phase 9 scales the phase 1 samples to every unit the Authority owns across HVAC, boarding bridges, baggage, vertical transportation and airfield, in the order the Authority sets.

  1. Sources
  2. Interchange
  3. Twin
  4. Screens
  5. Plan
Kind
Plan
Status
not linked
Airport layer
not linked
Airport area
not linked
System
not linked
Sensor type
not linked

Open the detail

Level 2 of 3 This component, complete on its own. Its files, sources and tests are the detail below. Open the detail

Phase 9 scales the phase 1 samples to every unit the Authority owns across HVAC, boarding bridges, baggage, vertical transportation and airfield, in the order the Authority sets. It brings in the next systems (terminal lighting, generator monitoring, parking, leasing) through the registry with approved exchange sheets, and loads the GIS roadmap's spatial updates.

Dates
2028-02-01 to 2029-01-31
Requirements delivered
5
Work units
9
Needs
Needs P8
Work units (9)
UnitTitleDatesRFPNeeds
WU-9-1Year 2 environment sizing and cost and health reporting2028-02-01 to 2029-01-31B vi, C 7.4
WU-9-2Authority priority order and unit onboarding pipeline2028-02-01 to 2029-01-31C 1.3, C 5.10DEP-22
WU-9-3HVAC and vertical transportation full unit onboarding2028-02-01 to 2029-01-31C 1.3, C 5.10DEP-22
WU-9-4Boarding bridge and baggage full unit onboarding2028-02-01 to 2029-01-31C 1.3, C 5.10DEP-22
WU-9-5Airfield full coverage2028-02-01 to 2029-01-31C 1.3, C 5.10DEP-22
WU-9-6Next systems exchange sheets and registry entries2028-02-01 to 2029-01-31C 6.7, C 6.9DEP-22
WU-9-7GIS roadmap spatial updates2028-02-01 to 2029-01-31C 4.4, C 7.4DEP-22
WU-9-8Point registry coverage reconciliation and scale verification2028-02-01 to 2029-01-31B vi, C 7.4
WU-9-9Year 2 support and sustainment2028-02-01 to 2029-01-31B v, C 7.4DEP-22
WU-9-1: Year 2 environment sizing and cost and health reporting

Depends on
none
Authority dependencies
none
Traces to
REQ-SFB-069
Functional requirements
4
WU-9-2: Authority priority order and unit onboarding pipeline

Load the Authority's year 2 order of work from the P8 roadmap as configuration and extend ingestion so units are onboarded in that order through the existing registry, gateway pattern and supplier standard.

Depends on
WU-9-1
Authority dependencies
DEP-22
Traces to
REQ-SFB-056
Functional requirements
3
WU-9-3: HVAC and vertical transportation full unit onboarding

Bring every chiller, air handler, elevator and escalator the Authority owns into the point registry from the phase 1 samples, with asset IDs placed in the hierarchy and live readings showing source and age.

Depends on
WU-9-2
Authority dependencies
DEP-22
Traces to
REQ-SFB-056
Functional requirements
4
WU-9-4: Boarding bridge and baggage full unit onboarding

Scale the Allen-Bradley bridge and conveyor samples to every boarding bridge and baggage line through the DMZ gateways, with the interface assessments repeated per unit.

Depends on
WU-9-2
Authority dependencies
DEP-22
Traces to
REQ-SFB-056
Functional requirements
3
WU-9-5: Airfield full coverage

Extend airfield inspections, pavement sections and lighting circuit status from the sample to every airfield asset, with each source showing its owner and the 3D airfield screen reflecting them.

Depends on
WU-9-2
Authority dependencies
DEP-22
Traces to
REQ-SFB-056
Functional requirements
4
WU-9-6: Next systems exchange sheets and registry entries

Draft and obtain Authority approval of exchange sheets for terminal lighting, generator monitoring, parking and leasing, and register each system's read-only points through the registry without code changes.

Depends on
WU-9-2
Authority dependencies
DEP-22
Traces to
REQ-SFB-026
Functional requirements
3
WU-9-7: GIS roadmap spatial updates

Load floor plans, base maps and asset mapping from the P5 GIS roadmap into the spatial inventory with metadata, and place newly onboarded units on the plans and in 3D.

Depends on
WU-9-3, WU-9-4, WU-9-5
Authority dependencies
DEP-22
Traces to
REQ-SFB-013, REQ-SFB-054
Functional requirements
0
WU-9-8: Point registry coverage reconciliation and scale verification

Verify the registry by class holds every unit the Authority owns, reconciles with Simplify i3 assets, and carries the load of 10,000 sensing points on the Asset Record screens.

Depends on
WU-9-3, WU-9-4, WU-9-5, WU-9-6, WU-9-7
Authority dependencies
none
Traces to
REQ-SFB-069
Functional requirements
0
WU-9-9: Year 2 support and sustainment

Provide year 2 support, upgrades, issue resolution and professional services, keeping the support log and the sustainment baseline that P10 continues.

Depends on
WU-9-1
Authority dependencies
DEP-22
Traces to
REQ-SFB-053, REQ-SFB-054
Functional requirements
4
Requirements delivered (5)
IdRequirementAcceptanceEvidence
REQ-IMP-057the environments stay healthy and the bill tracks the model.the monthly cost and health report.
REQ-IMP-058Every unit of the five first classes brought in, from a few of each to all of them, in the order the Authority sets.each class shows every unit the Authority owns.the point registry by class.
REQ-IMP-059The next systems recommended in phase 1 brought in where they add value: terminal lighting, generator monitoring, parking and leasing.each system joins through the registry with its exchange sheet.the exchange sheets.
REQ-IMP-060Spatial additions and updates from the GIS roadmap: floor plans, base maps and asset mapping.each update loads with its metadata.the spatial inventory.
REQ-IMP-061Support, sustainment and professional services for year 2.support terms met.the support log.