AirfieldpathOrlando Sanford International

6.14 · Data and sources · Research notes

Airport facilities

Desk research, read 2026-10-29 and 2026-10-30. Nobody was contacted. Every row names its source and carries a

No picture for this component.

Document · Data and sources · Research notes

Airport facilities

Desk research, read 2026-10-29 and 2026-10-30. Nobody was contacted. Every row names its source and carries a

  1. Sources
  2. Interchange
  3. Twin
  4. Screens
  5. Plan
Kind
Document
Status
not linked
Airport layer
not linked
Airport area
not linked
System
not linked
Sensor type
not linked

Open the detail

Level 2 of 3 This component, complete on its own. Its files, sources and tests are the detail below. Open the detail

Desk research, read 2026-10-29 and 2026-10-30. Nobody was contacted. Every row names its source and carries a confidence tag. Where a fact could not be confirmed, the row says "not confirmed".

How to read this file

Confidence tags:

TagMeaning
verifiedRead this session in a primary source with a text layer (the RFP, an agenda, an FAA or FDOT file, the registry's verified rows)
OCRRead in the macOS Vision OCR of a signed minutes scan. Check the page image before quoting it in the proposal
reportedRead in news or a trade article, or in a third party page
inferredOur reading of two or more facts. Not stated by any source
not confirmedLooked for and not found, or the sources disagree

Source shorthand. Minutes are cited by OCR file name and the scan's page number, for example 040726 p14 means docs/rfp/public/ocr/040726-Minutes-Final-Signed-1.txt, page 14. RFP means docs/rfp/2027-006-RFP/Airport_Digital_Twin_Platform_Implementation_and_Support_Services.txt. SOW means the RFP's Attachment C, 2027-006-RFP_-_Attachment_C_-_Detailed_Scope_of_Work.txt. Registry means docs/domain-registry.json (read only, not edited).

The OCR has known slips. "OSl" is OSI. "loppolo" is Ioppolo. Numbers in the scans were read as printed and some are inconsistent with each other; those are flagged in the rows.

1. The terminal

1.1 Layout, names and gates

#FactSourceConfidence
T1One commercial terminal today. The 2018 to 2021 project merged the former Terminal A and Terminal B into one buildingAirport Improvement, "Expansion, Renovations at Orlando Sanford Int'l..." (2023-01-01)reported
T2The same article places the former Terminal A on the west side and Terminal B on the east sideAirport Improvement (2023-01-01)reported
T3The minutes name the halves differently. The 2nd chiller is called both the "West Terminal 400-ton chiller" and "the 2nd chiller for Terminal B side". The playground is placed in "the east terminal" (Sept 2025) and "in Terminal B" (Dec 2025). OpenStreetMap labels Terminal A to the east of Terminal B. Which half is A today is not confirmedMinutes-Signed-040125 p10; Minutes-090225 p5; 120225 p5; poc/build/sfb-osm.jsonnot confirmed
T416 gates, able to take domestic and international operations2021 AMPU Vol. I, via registry term "sfb commercial terminal"verified
T5Before the expansion there were 12 gates. Four were added, extending from a hold area on the east sideAirport Improvement (2023-01-01)reported
T6The 2018 to 2021 project cost $60 million, added about 40,000 sq ft, expanded ticketing by about 14,000 sq ft and moved all ticketing to the west end. Funded by PFCs and FDOT grantsAirport Improvement (2023-01-01)reported
T7Gate numbers seen in the minutes: Gate 10 (upper level retail), Gate 12, Gates 4 to 16 (terminal ramp work)040726 p6; 120324 p4; Minutes-Signed-040125 p4OCR
T8A Federal Inspection Services (FIS) area for international arrivals. The newer baggage claim and the older arrivals area are split by the CBP facility, so passengers cannot walk end to end inside060226 p12OCR
T9Terminal address used by the Authority: 1200 Red Cleveland Blvd., boardroom on the 2nd floor of the main terminalRFP section 1.4 and 4.1verified
T10Total terminal floor areanone foundnot confirmed

1.2 Passenger boarding bridges

#FactSourceConfidence
B1Airlines use 16 jet bridgesFDOT FASP 2043 profile, via registry "sfb commercial terminal"verified
B2Maintenance is focused on "the 12 original units installed in 2013"; Director Smith put them at 12 to 15 years old040726 p14OCR
B3Ameribridge is named as the boarding bridge supplier for the 2018 to 2021 project. The count it supplied is not statedAirport Improvement (2023-01-01), facts sidebarreported
B412 units from 2013 plus 4 added in the expansion would make 16. This is arithmetic, not a sourceB1, B2, T5inferred
B5The make of the 12 units from 2013none foundnot confirmed
B6PBB controls are Allen-Bradley, "Not Connected"SOW section 6.9 tableverified
B7Jet bridge repairs drove Repairs and Maintenance 27% over budget (April 2026) and again in the July 2026 budget amendment040726 p8 and p14; 070726 p11 to p12OCR
B8The generator replacement project is titled "Generator Replacement (Admin/PBB)". In Sept 2026 it was finalizing construction with completion expected in September090126 p6OCR
Amendment addresses unexpected costs for jet bridge maintenance stemming from both deferred and routine requirements as well as minor facility improvements, such as exterior painting.

(040726 p14, OCR)

1.3 Baggage handling

#FactSourceConfidence
H18 inbound and 3 outbound baggage systems081225 p9 (George Speake)OCR
H2Six domestic claim carousels (three added in the expansion, made by Logan Teleflex, now Daifuku) and two international carouselsAirport Improvement (2023-01-01)reported
H3BHS controls are Allen-Bradley, "Not Connected"SOW section 6.9verified
H4Most BHS maintenance is in-house. Annual, quarterly and preventive inspections and larger repairs went to BMG Conveyor Services of Florida, dba Davis Industrial, contract SA-2025-047-CB, 3 years from 2025-08-12, $239,166081225 p9 to p10OCR
H5Two belts under the observation deck were out of service during its repair, which overworked a third belt. Belt 6 was to be rested while belts 7 and 8 returned to serviceMinutes-090225 p5; 081225 p9 and p18OCR
H6A "baggage hygiene policy" that regulates equipment use was written into the new Allegiant airline use agreement (June 2026)060226 p14OCR
H7Inline checked baggage screening equipment and its ownernone foundnot confirmed
We've had to do a lot of work since we took over, because again it was another system at the Airport that was not properly maintained.

(081225 p9, George Speake, OCR)

1.4 Elevators and escalators

#FactSourceConfidence
V1All escalators have been modernized; the last were completed in November (2024, from an April 2025 meeting)Minutes-Signed-040125 p4OCR
V2Elevator 1, "the old service elevator", modernization began April 2025 and was complete by August 2025. It had cost about $1,000 a week to keep runningMinutes-Signed-040125 p4; 081225 p4OCR
V3Elevator 10 (Welcome Center, at the rental car facility) modernization by Kone began the week of 2025-11-17 and was awaiting final inspections in January 2026Minutes-110425 p5; 120225 p23; 010626 p5; Minutes-Signed-040125 p11OCR
V4Elevator 5, beside the checkpoint escalators on the opposite side of the terminal, added to FDOT PTGA FM#456492-1-94-01 in June 2026. $220,000 total, $110,000 from FDOT, 50/50. Called the final terminal elevator needing modernization060226 p13OCR
V5Modernization keeps the cab and skeleton and replaces most controls and some hydraulics, so at least some units are hydraulicMinutes-Signed-040125 p4OCR
V6Total count of elevators, escalators and moving walkways, and the maintenance contractor of recordnone foundnot confirmed
This represents the final terminal elevator requiring modernization.

(060226 p13, OCR)

1.5 Central plant, chillers and HVAC

#FactSourceConfidence
C1Five terminal chillers sit under a single maintenance agreement070726 p11 (Jeremy Owens)OCR
C2Three were legacy 2008 units of 400 tons, "originally maintained by OSI". All three have now been replaced or awarded20260505 p24; 070726 p11OCR
C3Chiller 2 (West Terminal, 400 ton): Air Mechanical and Service Corp., $419,848, under FDOT PTGA FM#455305-1-94-01 (Resolution 2025-03, April 2025). Finished in May 2025Minutes-Signed-040125 p10; Minutes-Signed-050625 p8OCR
C4A rented emergency chiller ran at the West Terminal until 2025-05-09, at about $9,000 a week. Final cost $349,000 (Resolute Industrial dba Mobile Air and Power Rentals, SA-2024-048). July 2025 minutes give $342,000Minutes-Signed-060325 p12; 030425 p6; 070125 p6OCR
C5Chiller 1: installation complete by September 2025, awaiting controls081225 p18; Minutes-090225 p22OCR
C6Chiller 3 (east side of the terminal): Mechanical Services of Central Florida (EMCOR), $445,358, piggyback on Lake County Schools ITB 2025-019-ITB-KF949, July 2026. The FDOT PTGA amendment folds all three replacements into one grant at $440,000 total, 50% FDOT (May 2026). The two totals do not reconcile in the OCR070726 p11; 20260505 p24OCR
C7Building Management System is Schneider EcoStruxure, on the internal networkSOW section 6.9verified
C8A separate HVAC chillers and water circulating pumps PM contract was solicited in May 2025; its award was not foundMinutes-Signed-050625 p12OCR
C9Building 310 (UCF lease, off-terminal) renovation removes a legacy chiller and oil boiler for split systems, with a new 1,600-amp service010626 p5OCR
C10The make and tonnage of chillers 4 and 5, cooling towers, boilers and the plant's locationnone foundnot confirmed
Owens confirmed that a single maintenance agreement covers all five terminal chillers.

(070726 p11, OCR)

1.6 Other terminal works and systems

#FactSourceConfidence
O1Observation deck, "formerly known as the smoking deck". A 2019 to 2020 report found problems that OSI did not fix. Shoring went in about early 2024. Repair plans by CPH. Phase I structural by Mark Construction, WO 2025-MC-01 under SA-2025-023-CB (March 2025), Change Order 1 (Sept 2025). Steel done by August 2025, gutters by December 2025, "initial phases complete" January 2026030425 p16; Minutes-090225 p4; 120225 p4; 010626 p5OCR
O2Three planned phases: structure; roof and close in; then an air conditioned passenger space. Final use was "still up in the air" in Sept 2025Minutes-Signed-040125 p11; Minutes-090225 p5OCR
O3FDOT PTGA FM#456492-1-94-01 (Resolution 2025-04), 50/50, $460,000: observation deck, rental car facility column repairs, Elevator 10 and east terminal refurbishmentMinutes-Signed-040125 p10 to p11OCR
O4Oldest roof section, original from 1993, replaced with TPO (early 2025)030425 p7OCR
O5FIS: CBP required an overhaul in 2018, first scoped at $12 million 50/50 with FDOT. CBP later chose a refurbishment at about $3.5 million, and about $4 million went back to FDOT (PTGA 437713-2-94-01, Resolution 2026-03, April 2026). The FIS exit lane was due for occupancy Sept/Oct 2026040726 p13 to p14; 090126 p6OCR
O6"Block House" ramp building, used by OSI for ground handling, mold remediation and renovation: Mark Construction $699,040.90 plus about $130,000 electrical, about $830,000 total (Sept 2026)090126 p13OCR
O7Four overhead digital signs on Red Cleveland Blvd, installed under OSI, past service life ("the eBay stage of parts"). Replacement awarded to i2Visual, RFP 2025-024-RFP (Nov 2025), with RS&H as technical advisorMinutes-110425 p10 to p12OCR
O860,000 sq ft of re-lamping was under way in August 2025081225 p7OCR
O9Terminal lighting control is Acuity SensorSwitch, "Not Connected"SOW section 6.9verified
O10Plumbing lines descaled at BC1, Gate 12 and another location (Dec 2024)120324 p4OCR

1.7 Terminal A renovation, East Terminal Redevelopment and the ATP application

#FactSourceConfidence
A1A $45 million Terminal A renovation at SFB was not found in the minutes, the agendas or a web searchthis sessionnot confirmed
A2The "$45 million project" in the minutes is Diversified Aviation SFB Phase 1, a 23-acre Southeast Ramp hangar development (4 buildings, 31 hangars)040726 p19; 090126 p49OCR
A3WFTV reported a $45 to $50 million renovation at Orlando International (MCO), a different airport. This is a likely source of the mix-upWebSearch summary of a WFTV page (not opened)inferred
A4An older CEO interview speaks of a $70 million terminal expansion. The interview date is not knownCapital Analytics Associates page (search excerpt; the page returned 403)reported
A5President Martz described an Airport Terminal Program (BIL) application titled "Family Friendly Healthy Airports", with an East Terminal Redevelopment and family amenities010626 p18OCR
A6SFB's only ATP award found is FY2024: $1,000,000 for part of the West Terminal corridor rehabilitation, the passenger waiting area and ADA accommodations. SFB is absent from the FY2022, FY2025 and FY2026 selection lists. FY2023 was not checkedFAA ATP selection PDFs FY2022, FY2024 (rev 2025-02-14), FY25, FY2026 (2026-05-18), text searched; Rep. Mills release 2024-02-16verified
A7Whether the "Family Friendly Healthy Airports" application was selectedthe FY2026 list does not show SFBnot confirmed
East Terminal Redevelopment: Repurposing the former duty-free area to increase passenger capacity and restore airfield views by uncovering currently obstructed windows.
Family Amenities: Expanding the "Golden Age of Travel" theme by installing a new Play equipment in the West Terminal, complementing the recently completed East Terminal facility, and exploring the development of a sensory room.

(010626 p18, OCR)

2. The airfield

#FactSourceConfidence
F1Runway 9L/27R: 11,002 by 150 ft, asphalt, condition GOOD, HIRL, PCN 1490/F/A/X/T, 1,000 ft displaced threshold on 9LNASR cycle 2026-10-29, registryverified
F2Runway 9R/27L: 5,839 by 75 ft, asphalt, FAIR, HIRL; not available for Part 121 scheduled service over 9 seatsNASR, registryverified
F3Runway 18/36: 6,002 by 150 ft, asphalt and concrete, FAIR, MIRLNASR, registryverified
F4Runway 9C/27C: 3,578 by 75 ft, asphalt, FAIR, MIRLNASR, registryverified
F5Part 139 Class I, ARFF Index D (Index E with 24 hour PPR). Tower 0630 to 2300, Class C in those hoursNASR, registryverified
F6Acreage: NASR 3,000; the 2021 AMPU about 2,400. The sources disagreeregistry "sfb acreage"not confirmed
F7FAA hot spot HS 1 is Taxiway C and Runway 27C. The ALP consultant described a hot spot where Runway 27C and Runway 18/36 intersectFAA d-TPP 2611 SE-3 list, registry; 080426 p3verified (FAA); OCR (ALP)
F8Taxiways named in the minutes: A (Alpha), B and B7, C, K1 (removed during 9L work), L (Lima)Minutes-090225 p4; 070125 p5; 070726 p16OCR
F9FDOT Statewide Airfield Pavement Management, District 5 2022 report: SFB 11.4 million SF, 4 runways, inspected 2022. Runway PCI: 18/36 58, 9C/27C 63, 9L/27R 71, 9R/27L 68. Year 1 localized preventive estimate $309,450registry "statewide airfield pavement management program"verified
F10FDOT inspects on about a three year cycle, so a newer SFB inspection may exist. Its date is not confirmedregistry; FDOT pavement pagenot confirmed
F11Runway 9L rehabilitation: field work from January 2025, lighting, shoulder paving and grooving through late 2025, punch list and closeout by March 2026010725 p3; 100725 p7; Minutes-030326 p3OCR
F12Airfield lighting systems by type: HIRL on 9L/27R and 9R/27L, MIRL on 18/36 and 9C/27C (NASR). The Taxiway A extension adds lighting, signage and an airfield vault modification. A failed rotating beacon was replaced for $19,953.18 (May 2025)registry; Minutes-Signed-060325 p12; Minutes-Signed-050625 p15verified (NASR); OCR (minutes)
F13The airfield lighting control system make, the vault count and the approach lighting inventorynone foundnot confirmed
F14The Airport Layout Plan update concentrates on 18/36 and 9C. The 2021 master plan's removal of 18/36 with a longer 9R "doesn't make sense anymore". Staff wants to keep 18/36 as a crosswind and relief runwayMinutes-Signed-060325 p13; 010626 p19OCR
F15Air traffic control tower relocation is sited near the ARFF station and awaits the FAA five year planMinutes-Signed-060325 p13OCR
F16In May 2026 George Speake said SFB "falls under Class B airspace". NASR says Class C20260505 p15; registrynot confirmed

3. Capital projects, 2024 to 2027

All amounts as printed. "SAA" is the Authority's own money.

#ProjectWhat was approvedAmountFundingSourceConfidence
K1Taxiway Alpha rehabilitationAward to Halifax Paving, Jan 2025$6,589,268FAA AIP 3-12-0069-095-2025 from BIL money "that we have and are receiving", plus FDOT and local010725 p9 to p10OCR
K2Terminal apron (ramp) improvements, Gates 4 to 16C&S Task Order 16 for construction phase services, Jan 2025; closeout Aug 2025not statedPFC010725 p8; 081225 p4OCR
K3Southeast GA stormwater improvementsResolution 2025-02not statedFDOT PTGA FM#454731-1-94-01, 50/50Minutes-Signed-040125 p10OCR
K4Chiller 2see C3$419,848FDOT PTGA FM#455305-1-94-01Minutes-Signed-040125 p10OCR
K5Terminal deferred maintenance itemsResolution 2025-04$460,000FDOT PTGA FM#456492-1-94-01, 50/50Minutes-Signed-040125 p11OCR
K6Remote parking lot, about 800 spacesAward to Halifax, April 2025; PTGA amended April 2026; completion expected Nov/Dec 2026target near $6M (2025)FDOT PTGA FM#452985-1-94-01, 50/50; a 2024 Truist line of credit was tagged to it030425 p17; 040726 p15; 120324 p8; 090126 p5OCR
K7FY25 deferred maintenance capitalBudget raised from $2.6M to $3,457,040FDOT share printed as $875,040 in the narrative and $857,040 in the motionFDOT grants plus SAAMinutes-Signed-050625 p15OCR
K8Wildlife mitigation Phase I (Twy B/B7)Halifax base bid, June 2025$2.25M base; C&S $147,966.14FAA $2,161,942 (90%)Minutes-Signed-060325 p10OCR
K91,500 gallon ARFF truck (FAA)Oshkosh, June 2025$1,058,252FAA $952,427Minutes-Signed-060325 p11OCR
K101,500 gallon ARFF truck (state)Sole source Oshkosh, Aug 2025. Both trucks on site Sept 2026$1,040,000 appropriationState appropriation via Florida Department of Financial Services, balance SAA081225 p7 to p8; 090126 p5OCR
K11Taxiway Alpha extension designJune 2025C&S TO 8 $1,001,195FAA $903,025, AIP 3-12-0069-097-2025Minutes-Signed-060325 p12OCR
K12ALP update with narrativeJune 2025; preferred alternative Sept/Oct 2026; FAA pre-applications due Oct 1C&S TO 7 $627,450FAA $566,955, AIP 3-12-0069-098-2025Minutes-Signed-060325 p13; 090126 p5OCR
K13Taxiway Alpha West extension construction (to the west end of the runway from Lima)Halifax low bid $11.8M, July 2026$13.4M totalFAA $12,076,525; FDOT PTGA amendment (printed "#44443-2-94-01", number likely truncated in the scan) to offset the local match070726 p15 to p16; 060226 p13 to p14OCR
K14Terminal Connector Corridor (secure walk between the two arrival areas)Resolution 2026-07, June 2026$3.0MFDOT PTGA FM#455272-2-94-01 $1.5M; federal earmark $1.0M (Rep. Mills, through the FAA); local $0.5M060226 p12OCR
K15Elevator 5Resolution 2026-08$220,000FDOT $110,000 via FM#456492-1-94-01060226 p13OCR
K16Chiller 3Resolution 2026-05 (May) and award (July 2026)$445,358 award; $440,000 grant total for threeFDOT 50%20260505 p24; 070726 p11OCR
K17Stormwater pond ("kidney pond") upgradeSouthern Development and Construction, July 2026$2,129,177not stated070726 p10OCR
K18Midfield utility (S. Beardall Ave and Moores Station Rd)SanPik, Sept 2026$2,000,000 with contingencynot stated090126 p12OCR
K19Vehicle Movement Area TranspondersFAA grant, Aug 2026, 10% local match$110,261FAA080426 p20OCR
K20VMAT, state sideResolution 2026-13, Oct 2026 agendanot on agendaFDOT PTGA FM#458844-1-94-01100626-Agenda-Final.pdf item 10Bverified
K21Digital TwinGrant approval on the Oct 2026 agenda$1.2 millionState appropriation, through the Department of Management Services Technology Program (the minutes say State Office of Technology; corrected per the claims register); procurement by end of Sept 2026, completion by summer 2027100626-Agenda-Final.pdf item 10A; 060226 p12; 070726 p9verified (agenda); OCR (amount)
K22FY27 capital programResolution 2026-11, July 2026$14.1M total. CIP $8.1M with $1.2M SAA match; $3.3M departmental capex; $2.6M OSI deferred maintenancegrants plus SAA070726 p12 to p13OCR
K23FY27 named CIP projectsWildlife Phase II, obstruction removal, Runway 18/36 rehabilitation design, multimodal improvements, VMAT upgrades, Terminal Connector Corridor, rental car facility improvementsnot itemizedmixed070726 p13OCR

Federal programme totals that sit behind these rows:

#FactSourceConfidence
G1BIL AIG allocations to SFB: FY22 $5,670,156; FY23 $5,657,728; FY24 $5,564,345; FY25 $5,348,123; FY26 $5,188,866FAA AIG allocation PDFs, registryverified
G2AIP grant histories: FY2024 $11,620,521 (runway rehab, lighting, visual guidance, safety) and $1,000,000 terminal; FY2025 $6,539,635 AIG (reconstruct taxiway) and othersFAA AIP grant spreadsheets, registryverified
G3Staff said the AIG entitlement of about $5.6M a year had been banked since 2022 for Taxiway AMinutes-Signed-040125 p8OCR
G4An earlier $1M earmark for the corridor "punch thru" between the two baggage claims was lost in the continuing resolution and was to be resubmitted for FY26Minutes-Signed-040125 p8OCR
G5Florida law caps FDOT at 50% of the nonfederal share for an airport of SFB's size; most terminal deferred maintenance above is 50/50 FDOT state money with no FAA shareFla. Stat. 332.007(6), registry; rows K3 to K16inferred

The VMAT name conflicts. The Aug 2026 minutes and Oct 2026 agenda say Vehicle Movement Area Transponders. The FY27 budget passage in 070726 p13 reads "Vehicle Maintenance and Administration Terminal (VMAT) upgrades". Which project the FY27 line means is not confirmed.

4. Deferred maintenance and the end of the terminal contract

#FactSourceConfidence
D1The board voted on Sept. 18 to end the contract with Orlando Sanford International Inc. (OSI), "an entity owned by France-based Vinci Airports", citing 13 contract defaults tied to maintenance. Article dated 2023-12-10WFTV, "Sanford Airport Authority ends contract with terminal management firm"reported
D2Defaults named in the article: escalators, the parking garage, bag belts "and more". The full list of 13 is in the 2023-09-18 minutes, not read this sessionWFTV; minutes file 091823-Minutes-Signed.pdf on flysfb.com (not downloaded)reported
D3Deferred maintenance then: more than $26 million, 6.5 years into a 22-year contractWFTV (2023-12-10)reported
D4An effective end date of 2024-02-28 appeared in a search summary onlyWebSearch summarynot confirmed
D5April 2025: "we have $44M in deferred maintenance", with reserves drawn to cover itMinutes-Signed-040125 p7OCR
D6July 2026: an estimated $44 million to $55 million left by the former operator; $2.6 million a year budgeted against it070726 p12OCR
D7Sept 2026: the backlog "will still take years"090126 p9OCR
D8Items the minutes tie to OSI: three 2008 chillers and the rental chiller, the observation deck, Elevators 1, 5 and 10, BHS preventive maintenance, the overhead signs, the Block House, the 1993 roofrows C2 to C6, O1 to O7, V2 to V4, H4OCR
D9SAA v. TBI US Operations, Inc., Case 2024-CA-001039: settlement approved 2025-11-04 (Ioppolo opposed); check due in the November financialsMinutes-110425 p15; 120225 p8OCR
D10A separate OSI lawsuit continues. OSI claims $100 million in damages. Deadlines are stayed to January 2027; OSI targets a September 2027 trial and the Authority March 2028090126 p11OCR
D11Counsel advised that taking FDOT money for Elevator 5 should not bar recovery of deferred maintenance damages from OSI, subject to review060226 p13OCR
We will certainly try to bring you a budget this year that doesn't impact reserves but we have $44M in deferred maintenance.

(Minutes-Signed-040125 p7, President Martz, OCR)

President Martz concurred, explaining that staff is prioritizing items as quickly as possible, though addressing the backlog of deferred maintenance will still take years.

(090126 p9, OCR)

Board Director Smith asked for confirmation that we are keeping track of this deferred maintenance. Jeremy Owens confirmed.

(081225 p7, OCR)

5. The operating model

#FactSourceConfidence
M1The Authority, a special district created in 1971, owns and operates SFBRFP section 1; registry enabling actverified
M2From 1997 Airports Worldwide (AWW) held a concession for commercial air service, terminal management and cargo. AWW was later bought by Vinci Airports. OSI and TBI are the entities named in the minutessearch summary of ICAO case study, airportxnews and the 2019 and 2020 OSIA annual reportsreported
M3Wikipedia still says the airport is "operated by Airports Worldwide". The minutes show this is out of dateWikipedia; rows M4 to M6inferred
M4The Authority took over terminal management from OSI/TBI and kept the OSI team and three of its vendors010725 p8 to p9OCR
M5FY27 is "the Authority's third full fiscal year of direct operation following the management transition"070726 p14OCR
M6No terminal operator other than the Authority was found for 2026this sessionnot confirmed
M7Maintenance is run by Authority staff under the VP and Chief Development Officer (Jeremy Owens in the 2025 and 2026 minutes). Contractors cover specialist work: Davis Industrial (BHS PM), the chiller maintenance agreement, Kone (Elevator 10), TECC (electrical), Mark Construction (continuing construction), C&S and RS&H (engineering)rows H4, C1, V3; 081225 p6; 120324 p6OCR
M8Janitorial services are in-house20260505 p25OCR
M9Ground handling: Allegiant uses its own contractor (Worldwide Flight Services agreements, March 2026). The Authority handled other carriers and planned to move its ground handling to a third party from September 2026060226 p16; Minutes-030326 p3; 070726 p13OCR
M10FY27 personnel: 236 positions, concentrated in Airline Services, Operations and Maintenance070726 p13OCR
M11In May 2026 a director spoke of being "two years away from assimilating all Airport operations under one roof". What remains outside is not stated20260505 p12not confirmed

6. Traffic, airlines, cargo and research tenants

#FactSourceConfidence
P1Authority totals: passengers 2,941,456 (2023), 2,877,526 (2024), 3,166,417 (2025); operations 268,659, 310,074, 394,863flysfb.com statistics page, read 2026-10-30verified
P2FAA enplanements: CY2022 1,367,935; CY2023 1,446,884; CY2024 1,412,954; CY2025 1,553,711. Primary, small hub, rank 87FAA CY2025 file, registryverified
P3Record year 2019: 3,291,112 passengers. Peak operations 2001: 397,560. 2025 operations given as 394,002 at the January 2026 meeting010626 p18 to p19OCR
P4Busiest small hub by operations, 20th in the US through November 2025, 3rd in Florida010626 p19OCR
P52026-04-16: 110.5 operations an hour with the tower open20260505 p15OCR
P6Airlines page: Allegiant, Arajet, BermudAir, Contour (seasonal or charter), Sun Country (seasonal or charter)flysfb.com airlines page, registryverified
P7Allegiant has had hub operations at SFB since 2005 and is the signatory carrier under the first airline use agreement (June 2026, three year term, retroactive to Dec 1). SFB became Allegiant's second largest base after the Sun Country merger060226 p14 to p16OCR
P8BermudAir moves from MCO to SFB from October 2026 (Bermuda, then Belize in December). It flies four Embraer 190 and 175 aircraft with A220s on order. Its agreements were on the Oct 2026 consent agenda070726 p9; 100626-Agenda-Final.pdf item 6AOCR; verified (agenda)
P9Swoop, Flair and TUI left after the pandemic010626 p19OCR
P10Cargo: the Authority reports 0 tons for 2023 to 2025. A 20,000 sq ft cargo space was under lease negotiation in 2026flysfb.com statistics; 080426 p11verified; OCR
P11UCF CAPE (formerly CATER), former dorm building (Building 310): lease 2025-069 (Oct 2025), 5 years plus 5, over $600,000; SAA turnkey renovation, $5.5 million project; occupancy Sept/Oct 2026100725 p15; 090126 p6 and p49OCR
P12Siemens Energy molten salt storage research facility on Aviation Loop, footprint grown from 1 to 5 acres, $10 million, lease not final in Sept 2026080426 p11; 090126 p49OCR
P13Other aviation tenants: Million Air (FBO), Acron Aviation Academy, Flexjet, ASIG/Menzies, Avocet, AeroMech (38,000 sq ft hangar for a Starlink project), AirBoss MRO hangarregistry; 090126 p49verified; OCR

7. Ground access and rail

#FactSourceConfidence
R1SR 417 (Seminole Expressway) ends at I-4 in Sanford and is run by Florida's Turnpike EnterpriseCFX and FTE pages, registryverified
R2CFX SR 417 Sanford Airport Connector PD&E began May 2024, aims to relieve East Lake Mary Blvd, and is "upward of $200M". Presented to the Board May 2025Minutes-Signed-050625 p3 to p4OCR
R3Resolution 2025-06 (Oct 2025) supports Preferred Alignment 2A100725 p5OCR
R4January 2026: the Authority is working with Seminole County and CFX on multi-jurisdictional funding, using its federal lobbyists Alcalde & Fay. The OCR lists "two specific avenues" and then does not name them010626 p17OCR
R5June 2026: the City approved a joint funding agreement with the County for the connector, using gas tax revenue for up to ten years060226 p3OCR
R6SR 46 is the primary access to the north side parcels "due to the runway configuration"Minutes-030326 p9OCR
R7SunRail Sanford Station: 2720 W. State Road 46, with park and ride. The SunRail page lists no airport shuttleSunRail station page, registryverified
R8Distance from the terminal to SunRail Sanford by roadnot measurednot confirmed
R9Amtrak Auto Train southern terminal is in Sanford. Straight line from the OSM terminal centroid to the OSM "Sanford (Auto Train)" point is about 3.7 milespoc/build/sfb-access.json and sfb-osm.json (OSM); 060226 p19inferred
R10The CEO said in an interview that SFB is "the only Florida airport with a direct rail line" and that a rail line beside the airport was being explored. Aviation Week's profile words it as direct access to a CSX freight lineCapital Analytics excerpt via search (page not opened, undated); Aviation Week marketplace profile via searchreported
We are the only Florida airport with a direct rail line.

(Nicole Martz, Capital Analytics Associates interview, search excerpt only. Confirm against the full page.)

8. IT systems, maintenance software, GIS, CAD, BIM, drones and sensors

#FactSourceConfidence
S1Existing systems named by the Authority: Genetec Security Desk (video); Acuity SensorSwitch (terminal lighting); Allen-Bradley (BHS and PBB controls); Simplify i3 (work orders, safety management, inspections, partial asset management, cloud); PMX (real estate and leasing); Schneider EcoStruxure (BMS); Skidata (parking); Microsoft 365 Business Central (finance); generator monitoring (CAT, Genetec and others, not connected)SOW section 6.9verified
S2The RFP treats a CMMS/EAM as "foundational" and says the twin "shall not" replace it. Simplify i3 is the work order system the table namesSOW sections 5.4 and 6.2verified
S3A new ERP went live the weekend before the 2026-03-03 meeting. Its product name is not in the minutes. Business Central is the likely candidateMinutes-030326 p12; S1inferred
S4Amadeus ACUS cloud common use replaced the on-premise EASE system, contract SA-2025-016 (March 2025), for cyber security and maintenance reasons030425 p16OCR
S5GIS, CAD and BIM appear in the RFP as data the twin must take in, and the provider must assess "the current maturity of the Authority's GIS". No GIS, CAD or BIM system or file set is named in the minutesSOW lines 326 to 331, 464 to 470, 492; minutes searchverified (RFP); not confirmed (holdings)
S6The ALP drawing (signed 07/2022) and the master plan are public PDFsregistry "sfb airport master plan and alp"verified
S7Drones or UAS: no Authority drone programme was found in the minutes. The only hit is a student who earned an FAA drone certificate20260505 p3not confirmed
S8Sensors: the digital twin pitch to the Legislature named "integrated sensors to provide real-time data on all Airport facilities"010626 p17 to p18OCR
S9Vehicle movement area transponders on every ground vehicle in the movement area (grant Aug 2026)080426 p20OCR
S10A Board member asked for an internal KPI dashboard; staff is building "data center modeling" for expenditure metrics040726 p9; 060226 p8OCR
S11IT staff in the minutes: Tommy Gentry, Director of IT; Rhett Rabley, Assistant Director ITminutes attendance lists, e.g. 040726 p1, Minutes-110425 p1OCR
S12A 2023 RFI for an asset management system that integrates with Business CentralOpenGov project 42989, search summary in an internal note, held locallyreported
The current appropriation request is for the development of a "Digital Twin" system for the Airport. This Information Technology (IT) initiative utilizes integrated sensors to provide real-time data on all Airport facilities.

(010626 p17 to p18, OCR)

9. Facts to confirm at the 2026-11-06 site tour

  1. Which half of the terminal is called Terminal A today, east or west (T2, T3).
  2. Gate count and bridge count: 16 and 16, and the make and year of each bridge. Are the 12 from 2013 a different make from the expansion bridges (B1 to B5)?
  3. Elevator, escalator and moving walkway counts, their makes, and who holds the maintenance contract (V6).
  4. The five chillers: makes, tonnage, where the plant sits, and what the EcoStruxure BMS already reads from them (C1, C7, C10).
  5. Whether the BHS PLCs and PBB PLCs can be reached from a network at all, given "Not Connected" (B6, H3).
  6. Simplify i3: what asset hierarchy it holds, how many assets, and whether condition data is recorded (S1, S2).
  7. What GIS, CAD and BIM files exist for the terminal and airfield, and in what formats (S5).
  8. Whether any $45 million Terminal A renovation exists, or whether the figure is the Diversified hangar project (A1, A2).
  9. The outcome of the "Family Friendly Healthy Airports" ATP application (A7).
  10. The latest FDOT pavement inspection date and PCI for SFB (F9, F10).
  11. Which VMAT the FY27 budget means: transponders or a vehicle maintenance and administration building (K19 to K23).
  12. The full list of the 13 OSI contract defaults from the 2023-09-18 minutes (D2).
  13. The road distance and any shuttle between the terminal, SunRail Sanford and the Auto Train (R8, R9).
  14. Whether the Authority flies drones or has a UAS policy (S7).

Source file

FileSizesha256
sfb-facilities-2026-10-30.md36 KBd715163fa4098622289e53c268a83ddcf4c0e55d951b721965c6941240c13f24