Phase 11: Year 4: the gaps no maker sensor reaches, and more facilities

It surveys the assets that no maker data reaches and fills those gaps with commercial retrofit sensors first, with the Inflector offered as an option.

No picture for this component.

Plan · The RFP and the plan · Phases

Phase 11: Year 4: the gaps no maker sensor reaches, and more facilities

It surveys the assets that no maker data reaches and fills those gaps with commercial retrofit sensors first, with the Inflector offered as an option.

  1. Sources
  2. Interchange
  3. Twin
  4. Screens
  5. Plan
Kind
Plan
Status
not linked
Airport layer
not linked
Airport area
not linked
System
not linked
Sensor type
not linked

Open the detail

Level 2 of 3 This component, complete on its own. Its files, sources and tests are the detail below. Open the detail

It surveys the assets that no maker data reaches and fills those gaps with commercial retrofit sensors first, with the Inflector offered as an option. It also brings more facilities into the twin by configuration on the phase 1 standard, and continues support and sustainment for the year. Dates run 2030-02-01 to 2031-01-31.

Dates
2030-02-01 to 2031-01-31
Requirements delivered
4
Work units
10
Needs
Needs P10
Work units (10)
UnitTitleDatesRFPNeeds
WU-11-1Year 4 Order of Work and Scope Record2030-02-01 to 2031-01-31B v, B vi, C 5.10, C 7.4, RFP 3DEP-22
WU-11-2Scale Environments to 30,000 Sensing Points2030-02-01 to 2031-01-31B vi, C 7.4
WU-11-3Monthly Cost and Health Report Against the Model2030-02-01 to 2031-01-31B vi, C 7.4
WU-11-4Coverage Gap Survey of Assets With No Maker Data2030-02-01 to 2031-01-31C 2.5, C 5.10DEP-22
WU-11-5Retrofit Sensor Selection and Inflector Option2030-02-01 to 2031-01-31C 2.5, C 5.10DEP-22
WU-11-6Retrofit Sensor Fitting and Registry Onboarding2030-02-01 to 2031-01-31C 2.5, C 5.10DEP-22
WU-11-7Prediction Wiring for Retrofit Sensor Points2030-02-01 to 2031-01-31B vi, C 7.4
WU-11-8Additional Facilities Added by Configuration2030-02-01 to 2031-01-31C 5.10, RFP 3DEP-22
WU-11-9Year 4 Support, Sustainment and Professional Services2030-02-01 to 2031-01-31B v, C 7.4DEP-22
WU-11-10Year 4 Coverage Closeout for Phase 122030-02-01 to 2031-01-31B v, C 2.5, C 5.10, C 7.4, RFP 3DEP-22
WU-11-1: Year 4 Order of Work and Scope Record

Record the Authority's DEP-22 order of later work for year 4 and the P10 carry-over inputs so every other P11 unit starts from an agreed, dated scope.

Depends on
none
Authority dependencies
DEP-22
Traces to
REQ-SFB-053, REQ-SFB-054, REQ-SFB-056, REQ-SFB-069
Functional requirements
3
WU-11-2: Scale Environments to 30,000 Sensing Points

Depends on
WU-11-1
Authority dependencies
none
Traces to
REQ-SFB-069
Functional requirements
0
WU-11-3: Monthly Cost and Health Report Against the Model

Depends on
WU-11-2
Authority dependencies
none
Traces to
REQ-SFB-069
Functional requirements
4
WU-11-4: Coverage Gap Survey of Assets With No Maker Data

Compare the point registry, exchange sheets and P10 model cards with the asset hierarchy to list each asset that has no maker data or too little for prediction, and record it in a gap register (REQ-IMP-067).

Depends on
WU-11-1
Authority dependencies
DEP-22
Traces to
REQ-SFB-042
Functional requirements
0
WU-11-5: Retrofit Sensor Selection and Inflector Option

Name a commercial retrofit sensor option for each surveyed gap and document the Inflector as an offered alternative for the Authority to choose.

Depends on
WU-11-4
Authority dependencies
DEP-22
Traces to
REQ-SFB-042
Functional requirements
4
WU-11-6: Retrofit Sensor Fitting and Registry Onboarding

Obtain Simplify i3 asset IDs, fit the chosen retrofit sensors through the existing gateways and register their points read-only under the supplier standard and conformance test.

Depends on
WU-11-2, WU-11-5
Authority dependencies
DEP-22
Traces to
REQ-SFB-042
Functional requirements
4
WU-11-7: Prediction Wiring for Retrofit Sensor Points

Connect the new retrofit points to person-confirmed prediction under the model way chosen in DEP-15, with model cards updated and each call on the record.

Depends on
WU-11-6
Authority dependencies
none
Traces to
REQ-SFB-069
Functional requirements
4
WU-11-8: Additional Facilities Added by Configuration

Bring the facilities the Authority chooses into the twin on the phase 1 standard by configuration with no rebuild, and file a change record for each (REQ-IMP-068).

Depends on
WU-11-1, WU-11-2
Authority dependencies
DEP-22
Traces to
REQ-SFB-056
Functional requirements
4
WU-11-9: Year 4 Support, Sustainment and Professional Services

Deliver year 4 support, upgrades and professional services and keep the support log and sustainment history that feed the roadmap renewal (REQ-IMP-069).

Depends on
WU-11-2
Authority dependencies
DEP-22
Traces to
REQ-SFB-053, REQ-SFB-054
Functional requirements
4
WU-11-10: Year 4 Coverage Closeout for Phase 12

Verify the closed gaps and added facilities appear live with their sources on the registry and package the gap survey, change records and support log as hand-off evidence for P12.

Depends on
WU-11-3, WU-11-7, WU-11-8, WU-11-9
Authority dependencies
DEP-22
Traces to
REQ-SFB-042, REQ-SFB-053, REQ-SFB-054, REQ-SFB-056
Functional requirements
3
Requirements delivered (4)
IdRequirementAcceptanceEvidence
REQ-IMP-066the environments stay healthy and the bill tracks the model.the monthly cost and health report.
REQ-IMP-067The gaps no maker sensor reaches filled with commercial retrofit sensors first, and the Inflector offered as an option.a gap survey names each asset with no maker data and its retrofit option.the gap survey.
REQ-IMP-068More facilities brought into the twin at the Authority's choice, on the same standard.a new facility added by configuration.the change record.
REQ-IMP-069Support, sustainment and professional services for year 4.support terms met.the support log.