Phase 4: A few of each sensor type, end to end

Fits outbound-only edge gateways in the operational network's DMZ, then proves each of the five first asset classes (HVAC, boarding bridges, baggage, vertical transportation, airfield) with a small sample of real points and one added sensor where the source has none.

No picture for this component.

Plan · The RFP and the plan · Phases

Phase 4: A few of each sensor type, end to end

Fits outbound-only edge gateways in the operational network's DMZ, then proves each of the five first asset classes (HVAC, boarding bridges, baggage, vertical transportation, airfield) with a...

  1. Sources
  2. Interchange
  3. Twin
  4. Screens
  5. Plan
Kind
Plan
Status
not linked
Airport layer
not linked
Airport area
not linked
System
not linked
Sensor type
not linked

Open the detail

Level 2 of 3 This component, complete on its own. Its files, sources and tests are the detail below. Open the detail

Fits outbound-only edge gateways in the operational network's DMZ, then proves each of the five first asset classes (HVAC, boarding bridges, baggage, vertical transportation, airfield) with a small sample of real points and one added sensor where the source has none. Each sample is timed through the five-part chain from sensor to a person's action, which shows phase 1 rests on working end-to-end paths before dashboards, workflows and prediction are built on them in P5. The phase is bounded by the Authority's inputs (DEP-07 to DEP-12, DEP-16) and the 2027-06-30 funded window, so samples are kept small and certain.

Dates
2027-03-15 to 2027-05-14
Requirements delivered
7
Work units
8
Needs
Needs P3
Work units (8)
UnitTitleDatesRFPNeeds
WU-4-1OT DMZ edge gateways and gateway register2027-03-22 to 2027-04-09C 3.6, C 4.6DEP-07, DEP-11
WU-4-2Sample point ingest, normalisation and registry rows2027-04-12 to 2027-05-07C 1.3, C 6.6DEP-10
WU-4-3HVAC sample: chiller, air handlers and filter pressure sensor2027-04-05 to 2027-04-23C 1.3, C 3.3, C 6.3DEP-08, DEP-12
WU-4-4Boarding bridge sample and interface assessment2027-04-05 to 2027-04-30C 1.3, C 6.4, C 6.9DEP-09, DEP-12
WU-4-5Baggage conveyor sample and interface assessment2027-04-12 to 2027-04-30C 1.3, C 6.5, C 6.9DEP-09, DEP-12
WU-4-6Vertical transportation sample: elevator and escalator2027-04-12 to 2027-05-07C 1.3, C 6.6DEP-10
WU-4-7Airfield sample: inspections, pavement and lighting circuit2027-04-19 to 2027-05-07C 1.3, C 4.10, C 6.9DEP-04, DEP-16
WU-4-8Five-part chain timing and per-sample chain records2027-05-03 to 2027-05-14C 1.3, C 3.6, C 5.5
WU-4-1: OT DMZ edge gateways and gateway register

Fit outbound-only edge gateways in the operational network's DMZ, each publishing to the cloud with its own certificate and accepting no inbound connection, and record them with their firewall rules in a gateway register.

Depends on
none
Authority dependencies
DEP-07, DEP-11
Traces to
REQ-SFB-022
Functional requirements
3
WU-4-2: Sample point ingest, normalisation and registry rows

Build the ingest and normalisation path from the gateways into the per-class sample point store, registering each sample point in the source and point registry with its asset ID, source and age.

Depends on
WU-4-1
Authority dependencies
DEP-10
Traces to
REQ-SFB-020
Functional requirements
4
WU-4-3: HVAC sample: chiller, air handlers and filter pressure sensor

Read one chiller and two air handlers from EcoStruxure points and add one filter pressure sensor where the BMS has none, showing a live reading with source and age for each point.

Depends on
WU-4-2
Authority dependencies
DEP-08, DEP-12
Traces to
REQ-SFB-017, REQ-SFB-040
Functional requirements
3
WU-4-4: Boarding bridge sample and interface assessment

Assess the Allen-Bradley controls of one or two boarding bridges, read bridge status from the controls or a documented gateway route, and add one gearbox vibration sensor.

Depends on
WU-4-2
Authority dependencies
DEP-09, DEP-12
Traces to
REQ-SFB-018, REQ-SFB-040
Functional requirements
3
WU-4-5: Baggage conveyor sample and interface assessment

Read one conveyor line's status from its Allen-Bradley controls and add one drive vibration sensor, documented in an interface assessment.

Depends on
WU-4-2
Authority dependencies
DEP-09, DEP-12
Traces to
REQ-SFB-019, REQ-SFB-040
Functional requirements
0
WU-4-6: Vertical transportation sample: elevator and escalator

Read one elevator and one escalator from the maker's monitoring under the maintenance contract, showing status and service interruptions, with a named retrofit sensor as the fallback path the risk register already records.

Depends on
WU-4-2
Authority dependencies
DEP-10
Traces to
REQ-SFB-020
Functional requirements
4
WU-4-7: Airfield sample: inspections, pavement and lighting circuit

Place Simplify i3 airfield inspections on their assets, show pavement sections beside the published runway condition, and read one lighting circuit from a read-only report if the maker agrees, with a source register naming each source's owner.

Depends on
WU-4-2
Authority dependencies
DEP-04, DEP-16
Traces to
REQ-SFB-043, REQ-SFB-044, REQ-SFB-045
Functional requirements
4
WU-4-8: Five-part chain timing and per-sample chain records

Build the chain timer and produce a timed per-sample record showing a reading travelling from sensor through collector, cloud and cleaned data to a person's action, as evidence for REQ-IMP-030 and as input to P5.

Depends on
WU-4-3, WU-4-4, WU-4-5, WU-4-6, WU-4-7
Authority dependencies
none
Traces to
REQ-SFB-063
Functional requirements
4
Requirements delivered (7)
IdRequirementAcceptanceEvidence
REQ-IMP-024Edge gateways fitted in the operational network's DMZ, outbound only, one per zone needed by the samples.each gateway publishes to the cloud with its own certificate and accepts no inbound connection.the gateway register and the firewall rules.
REQ-IMP-025HVAC sample: one chiller and two air handlers read from EcoStruxure points, and one filter pressure sensor added where the BMS has none.each sample point shows a live reading with its source and age.the point registry rows.
REQ-IMP-026Boarding bridge sample: one or two bridges read from their Allen-Bradley controls, assessed first because C 6.9 lists them as not connected, and one gearbox vibration sensor added.one bridge's status read from its controls or a documented gateway.the interface assessment.
REQ-IMP-027Baggage sample: one conveyor line read from its Allen-Bradley controls, and one drive vibration sensor added.one conveyor line's status read.the interface assessment.
REQ-IMP-028Vertical transportation sample: one elevator and one escalator read from the maker's monitoring under the maintenance contract.one unit's status and service interruptions shown.the interface assessment.
REQ-IMP-029Airfield sample: airfield inspections from Simplify i3 placed on their assets, pavement sections shown beside the published runway condition, and one lighting circuit's status from a read-only report if the lighting system's maker agrees.an inspection in Simplify i3 appears on its place, and each airfield source shows its owner.the captures and the source register.
REQ-IMP-030Each sample sensor shown through the five parts of the chain: the sensor sending, the collector on site, the cloud, the data cleaned, checked and tagged, then the display where a person acts on it.for every sample, a reading travels from the device to a person's action, timed.the chain record per sample.