3.11 · The RFP and the plan · The plan
The implementation plan
12 phases and 100 work units, from the Authority's written authorization to go-live.
No picture for this component.
Plan · The RFP and the plan · The plan
12 phases and 100 work units, from the Authority's written authorization to go-live.
- Sources
- Interchange
- Twin
- Screens
- Plan
- Kind
- Plan
- Status
- not linked
- Airport layer
- not linked
- Airport area
- not linked
- System
- not linked
- Sensor type
- not linked
Open the detail
Level 2 of 3 This component, complete on its own. Its files, sources and tests are the detail below. Open the detail
| Phase | Title | Dates | Work units |
|---|
| P1 | Initiation and requirements validation | 2027-02-02 to 2027-03-05 | 8 |
| P2 | Environments, sign-in and the core platform | 2027-02-15 to 2027-03-26 | 9 |
| P3 | Integration proof | 2027-03-08 to 2027-04-16 | 9 |
| P4 | A few of each sensor type, end to end | 2027-03-15 to 2027-05-14 | 8 |
| P5 | Spatial, dashboards, workflows, use cases and the backlog | 2027-04-05 to 2027-05-28 | 10 |
| P6 | Training, documentation and knowledge transfer | 2027-05-10 to 2027-06-18 | 7 |
| P7 | Acceptance, go-live and the phase 1 close-out | 2027-05-17 to 2027-06-30 | 6 |
| P8 | Support and the next asset classes, rest of year 1 | 2027-07-01 to 2028-01-31 | 6 |
| P9 | Year 2: every unit of the five classes, and the next systems | 2028-02-01 to 2029-01-31 | 9 |
| P10 | Year 3: the wider terminal systems and prediction across classes | 2029-02-01 to 2030-01-31 | 10 |
| P11 | Year 4: the gaps no maker sensor reaches, and more facilities | 2030-02-01 to 2031-01-31 | 10 |
| P12 | Year 5: real-time data on all Airport facilities | 2031-02-01 to 2032-01-31 | 8 |
Each phase ends at a gate the Authority accepts. The dates are the plan as written and move with the award date.