AirfieldpathOrlando Sanford International

3.11 · The RFP and the plan · The plan

The implementation plan

12 phases and 100 work units, from the Authority's written authorization to go-live.

No picture for this component.

Plan · The RFP and the plan · The plan

The implementation plan

12 phases and 100 work units, from the Authority's written authorization to go-live.

  1. Sources
  2. Interchange
  3. Twin
  4. Screens
  5. Plan
Kind
Plan
Status
not linked
Airport layer
not linked
Airport area
not linked
System
not linked
Sensor type
not linked

Open the detail

Level 2 of 3 This component, complete on its own. Its files, sources and tests are the detail below. Open the detail

PhaseTitleDatesWork units
P1Initiation and requirements validation2027-02-02 to 2027-03-058
P2Environments, sign-in and the core platform2027-02-15 to 2027-03-269
P3Integration proof2027-03-08 to 2027-04-169
P4A few of each sensor type, end to end2027-03-15 to 2027-05-148
P5Spatial, dashboards, workflows, use cases and the backlog2027-04-05 to 2027-05-2810
P6Training, documentation and knowledge transfer2027-05-10 to 2027-06-187
P7Acceptance, go-live and the phase 1 close-out2027-05-17 to 2027-06-306
P8Support and the next asset classes, rest of year 12027-07-01 to 2028-01-316
P9Year 2: every unit of the five classes, and the next systems2028-02-01 to 2029-01-319
P10Year 3: the wider terminal systems and prediction across classes2029-02-01 to 2030-01-3110
P11Year 4: the gaps no maker sensor reaches, and more facilities2030-02-01 to 2031-01-3110
P12Year 5: real-time data on all Airport facilities2031-02-01 to 2032-01-318

Each phase ends at a gate the Authority accepts. The dates are the plan as written and move with the award date.