| M-001 | RFP 1.1 | Configure, integrate, deploy and support a commercially available Digital Twin Platform | Platform Family | standard | not offered |
| M-002 | RFP 1.1 | A common operational environment integrating information from selected airport systems | Terminal Assets Now, Systems of Record, Point Registry | standard | partly met |
| M-003 | RFP 1.1 | Enhanced visualization, analytics, dashboards, workflows and decision support | The Terminal in 3D, Trends and Alarms, Maintenance KPIs, Role Dashboards, Workflows, Predictive Maintenance | standard | partly met |
| M-004 | RFP 1.1; C 3.5 | Complement, not replace; existing systems remain authoritative systems of record | Systems of Record, Maintenance and Work Orders, Work Orders | standard | partly met |
| M-005 | RFP 1.2 | A foundation for a long-term capability that evolves | Implementation and Roadmap, Rules and Data Library | standard | partly met |
| M-006 | RFP 2.19 | System of Record defined as the authoritative source in its domain | Systems of Record, Point Registry | standard | partly met |
| M-007 | RFP 3, objective 1 | A scalable platform for operations, maintenance and asset management | Rules and Data Library, Platform Family | standard | target |
| M-008 | RFP 3, objective 2 | Visibility into assets, condition, status, maintenance and lifecycle | Asset Record, Terminal Assets Now, Maintenance KPIs | standard | partly met |
| M-009 | RFP 3, objective 3 | Better preventive and corrective maintenance through access to information | PM Calendar, Work Orders, Backlog, Predictive Maintenance | configured | partly met |
| M-010 | RFP 3, objective 4 | Integrate selected enterprise and operational systems | Systems of Record, Point Registry | integrated third-party | target |
| M-011 | RFP 3, objective 5 | Configurable dashboards, spatial visualizations, workflows, analytics and reporting | Role Dashboards, Workflows, Spatial Enablement | configured | partly met |
| M-012 | RFP 3, objective 6 | A sustainable platform that expands through integrations and use cases | Implementation and Roadmap, Support | standard | target |
| M-013 | RFP 3, objective 7 | Open, standards-based, interoperable, evolving without proprietary customization | Open Standards, Point Registry | standard | partly met |
| M-014 | RFP 3, objective 8 | A formal process repository for post-project operation and maintenance References: E2 REQ-SFB-049 | Implementation and Roadmap, Security and Administration | configured | target |
| M-015 | RFP 3, initial scope | Asset management optimization as the first focus | Asset Record, Work Orders, Maintenance KPIs | configured | partly met |
| M-016 | RFP 3, focus area | Vertical transportation (elevators, escalators, moving walkways) | Vertical Transportation, Trends and Alarms, Maintenance KPIs | integrated third-party | partly met |
| M-017 | RFP 3, focus area | Passenger boarding bridge systems | Boarding Bridges, Trends and Alarms | integrated third-party | partly met |
| M-018 | RFP 3, focus area | Baggage handling systems | Baggage Handling, Trends and Alarms | integrated third-party | partly met |
| M-019 | RFP 3, focus area | HVAC systems | HVAC and Building Management, Trends and Alarms, Predictive Maintenance | integrated third-party | partly met |
| M-020 | RFP 3, focus area | Airfield infrastructure | Airfield Now, Pavement, Airfield Lighting, Self-Inspection | standard | partly met |
| M-021 | RFP 3, focus area | Other assets identified during implementation | Point Registry, Rules and Data Library | configured | target |
| M-022 | RFP 3, planning | Project initiation; validate priorities; implementation approach and schedule | Implementation and Roadmap | configured | target |
| M-023 | RFP 3, configuration | Configure asset models, dashboards, workflows, reports, notifications, security and user interfaces | Role Dashboards, Workflows, Security and Administration, Asset Record | configured | partly met |
| M-024 | RFP 3, data integration | Integrate CMMS/EAM, BAS/BMS, HVAC, PBB, BHS, vertical transportation and others | Systems of Record, Point Registry | integrated third-party | target |
| M-025 | RFP 3, spatial | Incorporate GIS, CAD, BIM, LiDAR, imagery, floor plans, drawings, asset locations | Spatial Enablement, The Airport in 3D, The Terminal in 3D | configured | partly met |
| M-026 | RFP 3, dashboards | Role dashboards for engineering, facilities, maintenance, operations, IT and executives | Role Dashboards | configured | partly met |
| M-027 | RFP 3, use cases | Use cases for asset performance, maintenance optimization, status visibility, decision support References: E2 REQ-SFB-034 | Terminal Assets Now, Maintenance KPIs, Predictive Maintenance, Implementation and Roadmap | configured | partly met |
| M-028 | RFP 3, analytics | AI-enabled analytics where practical and beneficial | Predictive Maintenance, Trends and Alarms | standard | partly met |
| M-029 | RFP 3, training | Formal O&M processes, training and knowledge transfer | Implementation and Roadmap, Support | configured | target |
| M-030 | RFP 3, documentation | Implementation, configuration, integration and user documentation | Implementation and Roadmap | configured | target |
| M-031 | RFP 3, ongoing | Ongoing professional services for enhancements | Implementation and Roadmap, Support | configured | target |
| M-032 | RFP 3, characteristics | Commercially supported software; configuration before customization; open integration; sustainable support; measurable value; expansion | Platform Family, Open Standards, Maintenance KPIs | standard | partly met |
| M-033 | RFP 3, final paragraph | Base the solution on Attachment C; provide software, licences, configuration, integration, documentation, training, support | RFP Compliance | n/a | met |
| M-034 | RFP 4 | Meeting rooms and accommodation requests | | n/a | met |
| M-035 | RFP 5.1 | Draft Contract to follow by addendum | | n/a | target |
| M-036 | RFP 6.1 | Responses binding 120 days after the deadline | | n/a | target |
| M-037 | RFP 6.2 | Identify material assumptions, exclusions, constraints, dependencies, third-party requirements, risks and Authority resources | Implementation and Roadmap | n/a | met |
| M-038 | RFP 6.3; A 3 | Questions only through the portal by the deadline | | n/a | met |
| M-039 | RFP 6.5 | Consent to inquiry and verification | | n/a | target |
| M-040 | RFP 6.6 | Comply with all laws; hold licences and permits | | n/a | target |
| M-041 | RFP 6.7, 6.8, 6.9 | Public entity crimes, scrutinized companies, suspension and debarment certifications | | n/a | target |
| M-042 | RFP 6.10 | Non-discrimination | | n/a | target |
| M-043 | RFP 6.11; 10.2.2 | Insurance: CGL 1M and 2M, auto 1M, professional 1M, workers compensation, broker letter | | n/a | target |
| M-044 | RFP 6.12, 6.16 | Non-exclusive; no guaranteed work; priorities may change | Implementation and Roadmap | n/a | met |
| M-045 | RFP 6.15 | No work before contract and written authorization | Implementation and Roadmap | n/a | met |
| M-046 | RFP 7.1 | Disclosure warranty | | n/a | target |
| M-047 | RFP 7.2 | Files in Word, Excel, PowerPoint or PDF, unlocked, printable, 150 dpi | | n/a | target |
| M-048 | RFP 8.5; A 11 | Interviews and demonstrations 2027-01-11 and 12 for shortlisted firms; key personnel attend | RFP Compliance | n/a | partly met |
| M-049 | RFP 9 | Evaluation weights 15, 25, 20, 15, 10, 15 with page limits | RFP Compliance | n/a | met |
| M-050 | RFP 10.1.1 to 10.1.5 | Florida registration; not on the convicted, scrutinized, federal or FDOT suspension lists | | n/a | target |
| M-051 | RFP 10.2.1; B II i | Two-page statement of ability with digital twin or comparable experience | Platform Family | n/a | target |
| M-052 | RFP 10.2.3; B II iii | Proof of Florida business licensing | | n/a | target |
| M-053 | RFP 10.3; B I | Two-page letter of interest with the listed fields | | n/a | target |
| M-054 | B i; RFP 10.4.1 | Experience implementing digital twin, asset visualization or integrated OT platforms | Platform Family, Drone Operations | n/a | partly met |
| M-055 | B i; RFP 10.4.1 | Three to five projects of similar scope with client, dates, role, platform, integrations and references | | n/a | not offered |
| M-056 | B i | Implementation challenges and how they were resolved | | n/a | target |
| M-057 | B i | Organizational resources, partners and platform relationships | | n/a | target |
| M-058 | B ii | Describe the platform, modules, architecture, hosting model, licensing, third-party components | Platform Family, Open Standards | standard | target |
| M-059 | B ii | Show support for business value, simplicity, COTS, configuration first, systems of record, open integration, practical AI, spatial enablement | Maintenance KPIs, Role Dashboards, Systems of Record, Open Standards, Predictive Maintenance, Spatial Enablement | standard | partly met |
| M-060 | B ii | Integration and data approach: APIs, middleware, web services, event-driven methods, data readiness, dependencies, interoperability | Point Registry, Systems of Record | standard | partly met |
| M-061 | B ii | Spatial approach for GIS, CAD, BIM, LiDAR, imagery, floor plans, drawings, asset locations, O&M | Spatial Enablement, The Terminal in 3D | configured | partly met |
| M-062 | B ii | Capabilities for visualization, dashboards, workflows, reports, notifications, AI, security, administration, scalability | The Terminal in 3D, Role Dashboards, Workflows, Predictive Maintenance, Security and Administration | standard | partly met |
| M-063 | B ii; B III | Identify which capabilities are standard, configured, integrated third-party, custom or conceptual; justify custom work | RFP Compliance | n/a | met |
| M-064 | B iii | Recommend initial scope, priorities, systems, assets, integrations, use cases and spatial capabilities | Implementation and Roadmap | configured | partly met |
| M-065 | B iii | Address the terminal and airfield focus areas | Terminal Assets Now, Vertical Transportation, Boarding Bridges, Baggage Handling, HVAC and Building Management, Airfield Now | configured | partly met |
| M-066 | B iii | Phases, schedule, milestones, sequencing, testing and acceptance, deployment, transition | Implementation and Roadmap | configured | target |
| M-067 | B iii; C 4.5 | Approach, staffing, effort and Authority participation for data collection and consolidation; data readiness risks | Implementation and Roadmap, Intake | configured | target |
| M-068 | B iii | Authority resources, third parties, assumptions, exclusions, constraints, dependencies, risks, mitigations | Implementation and Roadmap | n/a | partly met |
| M-069 | B iii | Future roadmap for expansion | Implementation and Roadmap, Sensor Gaps (concept), Drone Operations | conceptual | partly met |
| M-070 | B iv; RFP 10.4.4 | Organization chart, key personnel, project manager, technical lead, resumes, availability, substitution process | | n/a | target |
| M-071 | B v; RFP 10.4.5 | Training for administrators and user groups | Glossary, Implementation and Roadmap | standard | partly met |
| M-072 | B v | Documentation and knowledge transfer for routine administration, users and dashboards | Implementation and Roadmap, Security and Administration | configured | target |
| M-073 | B ii; B v | Environments, monitoring, security and redundancy | Environments and Operations | standard | target |
| M-074 | B v; C 7.4 | Post-go-live support, upgrades, issue resolution, maintenance, enhancement and continuous improvement | Support | standard | partly met |
| M-075 | B v | Long-term maintainability, cost-effective administration, configuration-based expansion | Role Dashboards, Workflows | configured | target |
| M-076 | B vi; RFP 10.4.6 | Pricing form with base implementation and recurring costs, shown separately | | n/a | target |
| M-077 | B vi | Data support labour categories, rates and hours; optional services priced separately | Implementation and Roadmap | n/a | target |
| M-078 | RFP 10.5 | Miscellaneous questions on terminated contracts and surety | | n/a | target |
| M-079 | A 2 | Cone of silence: no contact with Board, evaluators or staff except through Procurement | | n/a | met |
| M-080 | A 5 | Public records: claim exemptions section by section with the statute | | n/a | target |
| M-081 | A 7 | Submit through the portal by the deadline | RFP Compliance | n/a | target |
| M-082 | C 1.1 | Terminal and airfield asset management integrating existing systems into one environment | Terminal Assets Now, Airfield Now | standard | partly met |
| M-083 | C 1.1 | An ecosystem that grows with integrations, enhanced analytics including intelligent visual analytics, and use cases | Implementation and Roadmap | configured | target |
| M-084 | C 1.2 | Work collaboratively; initial and ongoing professional services | Implementation and Roadmap, Support | configured | target |
| M-085 | C 1.3 | Phased implementation focused on performance monitoring, preventive, corrective and predictive maintenance, awareness and decision support | Implementation and Roadmap, Predictive Maintenance, Maintenance KPIs | configured | partly met |
| M-086 | C 1.3 | Five initial asset classes; sequence refined at initiation | Terminal Assets Now, Implementation and Roadmap | configured | partly met |
| M-087 | C 2.1 | Establish the platform: a common environment with spatial information | The Terminal in 3D, The Airport in 3D | standard | partly met |
| M-088 | C 2.2 | Visibility into utilization, condition, maintenance, performance, inspections, lifecycle | Asset Record, Maintenance KPIs | standard | partly met |
| M-089 | C 2.3 | Proactive maintenance; customer service, response times, availability, workflow | Maintenance KPIs, Backlog, Work Orders | configured | partly met |
| M-090 | C 2.4 | Integrate systems; do not replace monitoring, control or management systems | Systems of Record, HVAC and Building Management | standard | partly met |
| M-091 | C 2.5 | Dashboards, spatial mapping, AI analytics including intelligent visual analytics | Role Dashboards, Predictive Maintenance | standard | partly met |
| M-092 | C 2.6 | Timely information for decisions through dashboards, workflows, notifications, analytics | Duties and Deadlines, Workflows, Maintenance KPIs | configured | partly met |
| M-093 | C 2.7 | Commercially supported, configured with standard tools, vendor-agnostic | Open Standards, Rules and Data Library | standard | partly met |
| M-094 | C 3.1 | Business value first | Maintenance KPIs | n/a | partly met |
| M-095 | C 3.2 | Keep it simple and sustainable | | n/a | partly met |
| M-096 | C 3.3 | COTS preferred; standard capabilities; minimal custom development | Platform Family | standard | not offered |
| M-097 | C 3.4 | Configuration before customization | Role Dashboards, Workflows | configured | target |
| M-098 | C 3.5 | Existing systems remain systems of record | Systems of Record, Point Registry | standard | partly met |
| M-099 | C 3.6 | Open integration by standard interfaces, APIs, middleware, web services, event-driven methods | Point Registry, Open Standards | standard | partly met |
| M-100 | C 3.7 | Practical AI: predictive maintenance, performance analysis, patterns, trends, recommendations, decision support | Predictive Maintenance | standard | partly met |
| M-101 | C 3.8 | Spatial enablement across GIS, CAD, BIM, LiDAR, imagery, plans, drawings, utilities, O&M; organized for each user group | Spatial Enablement, Role Dashboards | configured | partly met |
| M-102 | C 4.1 | Project initiation activities | Implementation and Roadmap | configured | target |
| M-103 | C 4.2 | Requirements validation without an extensive study | Implementation and Roadmap, RFP Compliance | configured | target |
| M-104 | C 4.3 | Configure object models, hierarchy, spatial, dashboards, rules, workflows, UI, notifications, reports, administration, security | Asset Record, Role Dashboards, Workflows, Security and Administration | configured | partly met |
| M-105 | C 4.4 | Incorporate spatial information; assess GIS maturity; roadmap for quality, completeness, governance | Spatial Enablement | configured | target |
| M-106 | C 4.5 | Identify, configure, test and implement interfaces; data support on request with job descriptions and rates | Systems of Record, Implementation and Roadmap | integrated third-party | target |
| M-107 | C 4.6 | Practical integration reusing existing interfaces; incremental addition | Systems of Record, Point Registry | integrated third-party | target |
| M-108 | C 4.7 | Interfaces with CMMS/EAM, BAS/BMS, HVAC, PBB, BHS, vertical transportation, VMS with analytics | Systems of Record, Point Registry | integrated third-party | target |
| M-109 | C 4.7 | Recommend information exchanges per system | Vertical Transportation, Boarding Bridges, Baggage Handling, HVAC and Building Management | configured | partly met |
| M-110 | C 4.8 | Dashboards and UI for each group, with maps, plans, status, alarms, work, trends, KPIs | Role Dashboards, Terminal Assets Now | configured | partly met |
| M-111 | C 4.9 | Configurable workflows for PM, corrective, requests, coordination, inspections, assessments, outages, notifications, approvals, tasks, follow-up, monitoring | Workflows, PM Calendar | configured | partly met |
| M-112 | C 4.10 | Initial use cases (fifteen listed) | Terminal Assets Now, Maintenance KPIs, Trends and Alarms, Implementation and Roadmap | configured | partly met |
| M-113 | C 4.11 | Training and knowledge transfer for each group | Implementation and Roadmap | configured | target |
| M-114 | C 5.1 | Enterprise asset visualization, spatial asset management, dashboards, roles, workflows, analytics, reports, notifications, integration, expansion | The Terminal in 3D, Asset Record, Role Dashboards, Workflows | standard | partly met |
| M-115 | C 5.1 | Desktop and web access; mobile where appropriate References: E1 REQ-UI-008 | Self-Inspection | standard | target |
| M-116 | C 5.2 | Incorporate GIS, CAD, BIM, LiDAR, plans, drawings, layouts, locations, O&M, imagery, CCTV and analytics | Spatial Enablement, Security and Administration | configured | partly met |
| M-117 | C 5.2 | Do not require every source before implementation | Spatial Enablement | standard | partly met |
| M-118 | C 5.3 | Asset identification, location, attributes, relationships, status, condition, history, inspections, maintenance history, trends, lifecycle | Asset Record | standard | partly met |
| M-119 | C 5.3; C 5.4 | Asset records, work orders, PM calendar, backlog, trends, alarm logs and KPIs in the shape maintenance staff know | Asset Record, Work Orders, PM Calendar, Backlog, Trends and Alarms, Maintenance KPIs | standard | partly met |
| M-120 | B ii; C 2.7 | Rules and data loaded as versioned packs, each in its true state, each rule traced to its screens; a duty register | Rules and Data Library, Duties and Deadlines | standard | partly met |
| M-121 | C 5.4 | CMMS/EAM integration is foundational: work requests, orders, PM, corrective, assets, schedules, inspections, history, labour, status, condition, documents | Work Orders, PM Calendar, Maintenance and Work Orders | integrated third-party | partly met |
| M-122 | C 5.4 | Complement the CMMS/EAM, never replace its core functions | Work Orders | standard | partly met |
| M-123 | C 5.5 | Systems integration with status, state, alarms, faults, availability, performance, events, indicators, energy | Vertical Transportation, Boarding Bridges, Baggage Handling, HVAC and Building Management, Trends and Alarms | integrated third-party | partly met |
| M-124 | C 5.6 | Dashboards with maps, plans, locations, indicators, colour-coded conditions, charts, trends, KPIs, alarms, maintenance and work summaries | Terminal Assets Now, Trends and Alarms, Maintenance KPIs, Role Dashboards | standard | partly met |
| M-125 | C 5.6 | Dashboards for engineering, facilities, operations, leasing and concessions, executives | Role Dashboards | configured | partly met |
| M-126 | C 5.7 | AI and analytics: predictive maintenance, performance, failure trends, alarm prioritization, patterns, recommendations, capacity, optimization, decision support, natural language query | Predictive Maintenance, Trends and Alarms | standard | partly met |
| M-127 | C 5.8 | Workflow management with approvals and escalation | Workflows | configured | partly met |
| M-128 | C 5.9 | Authentication, roles, administrative controls, audit logging, activity tracking, enterprise identity | Security and Administration | standard | partly met |
| M-129 | C 5.10 | Expansion to more systems, facilities, terminals, assets, dashboards, workflows, analytics, use cases, emerging technologies | Rules and Data Library, Implementation and Roadmap | standard | target |
| M-130 | C 6.1 | Evaluate each interface and recommend the approach; systems remain the record | Systems of Record, Point Registry | integrated third-party | target |
| M-131 | C 6.2 | CMMS/EAM information to present (records, hierarchies, locations, requests, orders, PM, corrective, inspections, history, condition, availability, documents) | Asset Record, Work Orders | integrated third-party | partly met |
| M-132 | C 6.3 | BAS/BMS and HVAC information (status, health, alarms, environment, energy, runtime, availability, indicators, faults) | HVAC and Building Management, Trends and Alarms | integrated third-party | partly met |
| M-133 | C 6.4 | Boarding bridge information (status, availability, assignments, alarms, maintenance, faults, indicators, history, inspections) | Boarding Bridges | integrated third-party | partly met |
| M-134 | C 6.5 | Baggage information (status, conveyor status, alarms, faults, maintenance, performance, events, condition, trends) | Baggage Handling, Trends and Alarms | integrated third-party | partly met |
| M-135 | C 6.6 | Vertical transportation information (status, availability, alarms, faults, inspections, history, performance, condition, interruptions) | Vertical Transportation | integrated third-party | partly met |
| M-136 | C 6.7 | Additional systems may be recommended: VMS, security, fire alarm, electrical, utility, passenger and flight information, energy | Implementation and Roadmap, Systems of Record | integrated third-party | target |
| M-137 | C 6.8 | Section missing from the document | | n/a | target |
| M-138 | C 6.9 | Representative systems: Genetec, Acuity SensorSwitch, Allen-Bradley BHS and PBB, Simplify i3, PMX, Schneider EcoStruxure, Skidata, Business Central, generator monitoring | Systems of Record, Point Registry, Rules and Data Library | integrated third-party | partly met |
| M-139 | C 7.1 | Deliverables: Implementation Plan, configured platform, object models, dashboards, workflows, reports, rules, integrations, security, user acceptance support | Implementation and Roadmap | configured | target |
| M-140 | C 7.2 | Concise documentation (configuration, integration, procedures, guidance, architecture, interfaces, training) | Implementation and Roadmap | configured | target |
| M-141 | C 7.3 | Training for administrators, engineering, facilities, maintenance, operations, IT, executives | Implementation and Roadmap | configured | target |
| M-142 | C 7.4 | Ongoing enhancement and sustainment services (dashboards, workflows, integrations, use cases, AI, performance, UI, configuration, spatial, support, knowledge transfer, roadmap planning) | Support, Implementation and Roadmap | configured | target |
| M-143 | Beyond the RFP | A platform proven on other places | Platform Family | conceptual | partly met |
| M-144 | Beyond the RFP | Drone inspections of the airfield | Drone Operations, Inspection Mission, Drone Cockpit | conceptual | target |
| M-145 | Beyond the RFP | Sensors where no maker data reaches | Sensor Gaps (concept) | conceptual | target |
| M-146 | Beyond the RFP | Grant evidence for AIP, infrastructure law programs and FDOT grants | Grant Opportunities, Grant Application, Grant Pipeline | standard | partly met |
| M-147 | Beyond the RFP | Part 139 records: self-inspection, condition reporting and NOTAM drafts, SMS | Self-Inspection, Condition and NOTAMs, Safety Management, Duties and Deadlines | standard | partly met |